
392
of which, practically with the minimum expenses,
coincides with a direction of a berthing line.
2 CONSTRUCTION OF THE OIL TERMINAL
AND PORT KULEVI
The basic criteria at construction of the oil terminal
and port were: taking into account the natural and
climatic conditions for creation protected from ex-
citement and sediments of aquatory with the least
volume of dredging operations; preservation of the
region’s ecosystem; construction of the oil terminal
on handling and to storage of oil; construction of
new port - Kulevi with a navigation channel;
maintenance with the terminal and port processing
of tankers given in table 1.
Table 1. Types of tankers are processed with the terminal and
port
___________________________________________________
Deadweight 100.000 40.000 28.700 17.100 7.600
(t)
Length Overall 250.0 195.0 179.0 151.5 114.6
(m)
Breath Mounded 42.2 28.0 25.3 22.4 16.5
(m)
Max. Draft 15.0 12.2 11.0 8.7 6.0
Loaded (m)
___________________________________________________
Construction of port and the terminal was simul-
taneously carried.
Territory of port occupied approximately 10 acre,
and the terminal of 173 acre. In this territory the sea
level from a chart datum on long-term supervision
varies from 0.1 up to 1.0 meters. Because of a wave
mode of the sea and prevention of flooding from the
mouth of the river Khobi territories of port, the deci-
sion to raise safe height construction from a chart
datum up to 2.5 meters it was accepted. In the be-
ginning of construction approximately 11000 m³ of
the vegetative layer of a ground (sickness of 0.5 me-
ter), was removed. For formation of the construc-
tion areas approximately 70000 m³ of a sandy
ground were covered. Dredging operations at the
right coast of a mouth river Khobi and directly in
aquatory of the future port were carried out with the
help of dredgers and dredges allowing the increasing
of the width of aquatory up to 290 meters. The de-
sign of a mooring facility of port was constructed in
the following sequence: creation of an obverse wall
by immersing of piles from metal grooves, marks
LX-32, alternation 27 and 25 meter piles; immersing
of piles from metal pipes diameter 820 mm on depth
up to 25 meters in a unloading wall; immersing of
piles from metal pipes diameter 1020 mm on depth
up to 27 meters in anchor wall; dredging from pipes,
using grab plant; installation channel frames in
heads of piles from pipes with concreting; installa-
tion of an obverse distributive belt; dredging under
anchor bar; stacking of wooden nozzles under an-
chor bar; installation anchor bar using the crane with
their tension; concreting anchor beams; covering
anchor bar a sandy ground with a layer not less than
1 meter; concreting head a mooring; dribble feed
bosoms of a mooring up to a bottom of a final cover-
ing with level-by-level condensation; arrangement of
a mooring after the end of dredging operations at a
mooring and in water area of port.
As a result of the made construction the new oil
terminal and port Kulevi consists of:
− The oil terminal on handling and to storage of oil
distributed in 16 shore tanks, each in volume of
20000 m³ (see fig. 2);
− A complex of hydraulic engineering constructions
providing unloading of oil from railway or road
transport to shore tanks, communication with ob-
jects of a tank farm, transportation of oil to moor-
ings and their loading on tankers;
− Hydraulic engineering constructions, which con-
sist of: mooring №1 for reception of vessels by
deadweight 100000 т., mooring №2 for reception
of vessels by deadweight 40000 т. and mooring
№3 for vessels of auxiliary fleet (see fig. 3, 4);
− A navigation channel, including: the entrance
channel, manoeuvring space – swinging room
(swinging pool) and operational space at moor-
ings (see fig. 5).
Figure 2. Shore tanks of oil terminal
Figure 3. Hydraulic engineering constructions