29
When sailing close to the geometric restriction,
ships needed to pass while being perfectly aligned
under the bridge Pont des Invalides. Due to the
presence of the arch bridge Pont Alexandre III, which
was located only 200 m further upstream, the ship
would have had to make a quick zig zag manoeuvre
to be able to pass while being centred under both
bridges. This manœuvre was not feasible for container
ships of 86 m and any ship longer than 110 m.
Container ships of 125 m with a beam of 9.65 m
encountered also some difficulties in between the two
islands due large drift effect induced by high current
speeds at the exit of the second bend where the arch
bridge Pont d’Arcole is located which was the first
bottleneck for this ship. Those difficulties could also
be observed with the other tested ships, nevertheless,
they happened at higher water levels than the limits
identified at the bridge Pont des Invalides and were
not considered as a bottleneck for those other ships.
3.5 Challenges
3.5.1 Air draft definition
At very high water levels, the headroom under
bridges was reduced so much that skippers adapted
their trajectory based on the air draft of each ship
model and therefore this parameter needs to be
defined with care prior the simulations and in the
analysis of the results. For instance, bulk carriers
might be able to sail with some eccentricity under
bridges while container ships would have needed to
be centred during the full passage, as showed in this
phase of the study with the succession of the two arch
bridges Pont Alexandre III and Pont des Invalides.
The maximum water level at which a ship would
be able to sail would strongly depend on the actual air
draft of the ship and the ballasting possibilities.
Hence, when presenting the results to skippers,
questions about the validity of conclusions for ships
with reduced air draft or increased ballast were
raised. However, both air draft and ballast can vary
significantly for a ship and standards are difficult to
find, as investigated by PIANC [7].
For this study, the air draft of the different ship
models had been tuned after consultation with the
client and the pilots involved in the study in order to
be compatible with the air draft of the actual fleet in
Paris. Of note, the minimum height of the ship
wheelhouse may vary from one region to another. For
instance in Belgium, class Va vessels generally have a
higher wheelhouse (e.g. 8 m measured from the keel)
than in France. The wheelhouse of the self-propelled
container ship model used in this study could be
lowered almost to the level of the containers, so that
the wheelhouse top was at 6.45 m measured from the
keel and the top of the containers layers was at 5.80 m
measured from the keel. This gave very low visibility
for the skipper, which was critical because the use of
radar was forbidden in Paris. In practice, under low
bridges, the skippers would usually lower the
wheelhouse as low as possible and steer the ship by
passing their head through a hatch, as described in
the first phase of the study [1]. The height of the self-
propelled bulk carriers had been set at 5.70 m
measured from the keel (i.e. with an air draft of 4.00 m
for a draft of 1.70 m). Hence, in this study, the air draft
was defined by the height of the wheelhouse.
For smaller beams, for which the bottleneck is
related to simple geometric consideration under the
bridge Pont des Invalides, skippers could easily
estimate their water level limits depending on their air
draft. However, for wide ships the maximum water
level limits were more difficult to estimate by
considering only the air draft of the ship. Indeed, the
bottleneck was related to difficulties to pass aligned
due to the small available width under the bridge
Pont Neuf whereas ships with a smaller beam could
sail with a large drift angle and pass without being
aligned.
Although the air draft is ship dependent,
simulations investigating bottlenecks above the
waterline (e.g. arch bridges) should be executed in
those loading conditions where the air draft is
expected to be at a maximum on the waterway in
order to be able to draw generic conclusions.
3.5.2 Human factor
As described in the first phase of the study [1],
skippers used different techniques to tackle a specific
bottleneck. In this phase of the study, the influence of
human factor could be identified between the bridge
Pont Alexandre III and the bridge Pont des Invalides.
Since the headroom of the bridge Pont Alexandre III
was higher than under the bridge Pont des Invalides,
skippers with ample experience with this passage
could avoid the zigzag manoeuvre by sailing as off-
centre as possible under the bridge Pont Alexandre III
to be able to pass perfectly aligned with the bridge
Pont des Invalides, as shown in Figure 6. This
technique required a good estimation of the available
space under the bridge Pont Alexandre III and was
obviously limited to certain water levels and certain
ships and was strongly dependent on the air draft. It
is clear that allowing navigation at such water levels
for these ships to new skippers with no prior
experience of sailing in Paris who might not anticipate
these bottlenecks, would be dangerous. Therefore a
certification system (in which the waterway manager
would make an exception for a ship exceeding the
maximum dimensions allowed), training strategy (e.g.
by using ship handling simulators) and other
recommendations were formulated when the
accessibility could not immediately be validated
based on simulation results.
Figure 6. Simulation of a 9.65 m wide ship sailing with an
eccentricity under the bridge Pont Alexandre III to be
perfectly aligned with the bridge Pont des Invalides.